November 12, 2026
The first thing Pender County plans to build at Long Creek Community Park is a playground. It will go on the former site of the Long Creek-Grady School at 23280 NC Highway 210 in Rocky Point, and a line in this year's state budget is paying for it. Everything else at the park, including walking trails, restrooms, shelters and fitness areas, is tied to a separate grant the county may apply for later.
Pender County has built a park this way before. Central Pender Park, up US 117, opened in August after a phased build that leaned on the same state grant program and slipped its first opening date. Its history is the best guide to how the Highway 210 site will develop over the next few years, and its fields and shelter are the nearest new place to play while Long Creek is still a plan.
In July, Pender County announced $620,000 in directed appropriations through the 2026 Appropriations Act, the state budget Governor Josh Stein signed that month. The county credited its legislative delegation, Representative Carson Smith and Senator Brent Jackson, for including the requests. The money splits three ways:
| Appropriation | Amount | What it covers |
|---|---|---|
| Playground Equipment and Improvements | $350,000 | Repairs at county-owned playgrounds plus new playgrounds in the Maple Hill and Long Creek communities |
| Various Grants | $200,000 | Twelve organizations, from WARM to the Penderlea Homestead Museum |
| Public Safety Equipment | $70,000 | An SCBA fill station for Emergency Services on the county's west side |
The county's announcement explains why recreation got the largest share. For the 2026 budget cycle, local appropriation requests could not include K-12 public education funding or utility infrastructure funding, so Pender's requests went to recreation, community organizations and public safety. A playground in Long Creek was the kind of project that fit the rules this cycle.
That $350,000 also has to stretch. It covers site repairs at existing county playgrounds and new playgrounds in two communities, Maple Hill and Long Creek. The county said it would share the playground timeline once it works out the terms with the state offices that administer the money.
In late August, the county invited residents to a drop-in session scheduled for Thursday, Sept. 10, from 4 to 6 p.m. at the park site. The session had two goals. One was gathering ideas for the playground's features, accessibility and age-appropriate play elements. The other was collecting input on the park's long-term vision. Parks and Recreation Director Zach White described the project in plain terms in WECT's coverage of the session:
"This playground is an exciting investment in our community, and we want the people who will use it to help shape it."
The second goal carries more weight for the park's future. The county said the long-term input will inform a potential application to the North Carolina Parks and Recreation Trust Fund, known as PARTF, for walking trails, restrooms, picnic shelters, open green space, fitness areas or other features the community identifies. WECT reported earlier in August that the county was exploring that PARTF route for future Long Creek amenities.
The playground is the funded piece. Whatever the old school grounds become after that will rest on a grant application the county builds from Rocky Point's input.
Central Pender Park sits at 3378 US Highway 117, about three miles north of Burgaw, and was planned to serve residents in the western part of the county. PARTF also helped pay for it. Its 2026 timeline shows the order a phased county park tends to follow:
Two parts of that timeline apply directly to Long Creek. Central Pender's opening slipped by more than six months because of a utility problem, the sewer redesign that followed the failed septic soil. The 2026 appropriations rules also left out utility infrastructure, so whenever restrooms reach Long Creek's plans, they will need funding from a source like the PARTF application the county described. And when Central Pender opened, it was usable but still unfinished. In the county's opening announcement, White called the opening "a milestone that has been a long time coming for our community" and said the county was opening the park while "a few amenities are still being completed."
While Long Creek is still in planning, Central Pender Park is the newest county park within a drive up US 117. Phase one includes:
The shelter is next to the playground. It measures 24 by 65 feet and has power and lighting, which matters on short December days. Pender County Parks and Recreation rents it by the hour through its RecDesk facility page.
| Renter | Hourly rate |
|---|---|
| Pender County residents and nonprofits | $15 |
| Nonresidents | $20 |
| For-profit organizations | $30 |
At those rates, a three-hour birthday party for a resident family comes to $45 for the shelter. For field use, the department asks people to contact its office at 910-259-1330 or [email protected].
Two county events are coming up soon:
The next public milestone at Long Creek is the playground timeline, which the county said it would share after working out the appropriation's terms with the state. The longer-range one is the PARTF application the county described, built around the amenities residents suggested. PARTF funding helped make Central Pender Park possible, along with the playground, lighted shelter and walking path that are open there now. Pender County Parks and Recreation posts its updates on the county's News Flash page, the same page that announced the Long Creek input session.
A new playground and the plans behind it are part of what makes a corner of Rocky Point feel like home. If you're wondering how changes along NC 210 could affect your property's value, Stephanie Bolleyer will put together a local, no-pressure look at your home. Get your free home valuation.